 |
|
Bay
Village’s partially completed new police station on Wolf Road.
(Photo by Larry Bennet)
|
Bay
Village files $1.3-million lawsuit over new police station
By Erik J. Eakin
Bay Village
The
city of Bay Village has filed a lawsuit against the architect of
the new police station, seeking $1.3 million in compensation for
cost overruns and other problems.
In a lawsuit filed two weeks ago, the city alleges that Brandstetter
Carroll Zofcin was negligent in various design and construction
phases of the police station, which caused the city to incur substantial
cost overruns. BCZ officials are disputing the allegations, saying
the city is trying to make a "scapegoat" of the firm.
The new police station was initially budgeted at $6.5 million. After
all the remediation and delay costs are tallied, the cost of the
new station could easily top $8.2 million, according to estimates.
In the lawsuit, the city charges that BCZ selected and supervised
Solar Testing, the company hired to perform soil borings and analysis
on the site, and that Solar concluded the site was "appropriate
and adequate for construction of the project."
However, during the excavation of the foundation, construction company
Panzica "discovered a large quantity of unidentified fill material"
and stopped construction, according to the lawsuit.
A company brought in to access the problem determined "the fill
to contain household and miscellaneous debris…and concluded the
debris not suitable for construction" and recommended the material
be removed and replaced with clean fill.
(It should be noted that during discussions of the project, BCZ
was warned, repeatedly, that the site of the new police station
had formerly been the city's dump.)
Subsequently, the Ohio EPA determined that development on the former
landfill would require a special permit which took almost two months
to secure, the lawsuit said.
The city claims the cost for soil remediation and associated environment
services totaled more than $525,000, and those delay costs added
another $449,000 to the project.
Additionally, the suit charges that BCZ did not include necessary
cabling in the budget proposal, which resulted in another $275,000
cost overrun.
The lawsuit also charges that BCZ was negligent in the design of
the structure and failed to include sufficient steel supports, which
resulted in another $50,000 expenditure.
Law Director Gary Ebert said the city tried for many weeks to reach
agreement with BCZ, which also designed the city's Family Aquatic
Center, "but we were unsuccessful."
BCZ President Lawrence W. Brandstetter said in response to the suit
that his firm acted professionally.
"The Bay Village city attorney (Gary Ebert) has chosen to try to
make a scapegoat of Brandstetter Carroll Zofcin to cover up his
own inappropriate actions and ineptitude," Brandstetter said.
"The documented data will clearly show that the BCZ staff acted
professionally on the interpretation of data that was provided by
the city. This vicious attack on our people is most despicable and
we will defend them vigorously."
Ebert said the scope of the project has been scaled back to compensate
for the unexpected expenses.
The anticipated completion date for the project is now Nov. 25,
a full five months later than the original scheduled completion
date.
"From here on out we should not have any surprises," Ebert said.
In a related development, Cresco, the real estate company hired
by the city to sell the former Marathon gas station parcel, has
filed suit against the city for $23,400.
The lawsuit alleges the city bypassed the company and sold the parcel
directly to Dover Junction owner Ray Negrelli, and that it is entitled
to its 6 percent commission.
Ebert said the city is not liable for the commission because the
prospective tenant Cresco secured for the site "did not qualify
and was not acceptable," and that the tenant would have needed a
parking variance.
|