 |
| City
officials expect to spend about $275,000 to replace the running
track at the Fairview High School athletic field. (West Life
photos by Kevin Kelley) |
City
to replace running track at Fairview High School
By Kevin Kelley
Fairview Park
Published July 28, 2010
City Council
expects to spend about $275,000 to redo the running track at the
athletic field adjacent to Fairview High School.
Council members
unanimously approved the expenditure at a special meeting July 21.
The city will begin accepting bids over the next two weeks.
While much of
the track is in good shape, several spots in front of the home stands
have buckled, causing a safety hazard for athletes. Fairview Park
City Schools Superintendent Brion Deitsch told West Life high school
track officials have commented to school officials about the safety
hazard in recent years.
Over the summer,
the city had 10 borings made at various points on the track to check
the condition below the surface.
According to
city architect Jeff Grusenmeyer, the borings revealed the track
has been resurfaced several times. Two layers of asphalt, measuring
5 to 7 inches, were placed upon a clay base years ago. A 1-inch
rubber track was placed on that. Later, another inch of asphalt
was laid as a surface for the current latex rubber track.
Adding a new
layer now is not feasible, Grusenmeyer said, as the track will then
be too high compared to the surrounding area.
“That track
has lived its life,” he said.
 |
| The
track has buckled and been patched in several places, causing
a safety hazard to runners. |
Grusenmeyer recommended against simply removing the
current latex rubber track and replacing it. The best course of
action, he said, is to remove the top track, the top 1-inch layer
of asphalt and the rubber track beneath this.
The new track
would be a polyeurothane surface with a structural spray. Such a
surface is a little more expensive but lasts longer, Grusenmeyer
said.
Grusenmeyer
said the city considered six options, with cost estimates ranging
from $159,000 to $318,000.
Mayor Eileen
Patton agreed with the conclusion not to seek a short-term fix.
“Someday we’ll
be passing on our problems,” the mayor told council. “How many problems
have been passed down to us? We don’t want to do that.”
The city will
pay for the repairs with money received in a bonding company settlement after the first Gemini Center pool
contractor was fired after alleged breech of contract.
According to Finance Director Lisa Rocco, that settlement
money, currently in the recreation department construction fund,
can legally be used only for permanent improvements or the repayment
of debt for the recreation center.
Construction work will take six to eight weeks, including
a two-week period during which the new layer of asphalt must settle,
Grusenmeyer said.
The mayor said that in the future, the city may restrict
access to the athletic field, especially the track, to reduce wear
and tear.
Patton said
the city asked the Fairview Park City Schools if they would contribute
to the costs of the track repairs. According to Deitsch, board members
declined.
Although the
school district is by far the most frequent user of the track, ownership
of the athletic field was legally transferred to the city under
the Gemini Project contract.
Grusenmeyer
noted the city would have to invest funds in the track at some point
anyway because the contract required regular maintenance of the
athletic field.
The new track
will be red instead of black, which Grusenmeyer said will give it
a longer life because it absorbs heat better. The new track surface
will also better match Fairview High School’s team colors, Deitsch
noted.
|